Contingency or re-baselining, what’s the difference?

  • Reading time:4 mins read

I’ve seen a few projects where customers said they didn’t need contingency, because they decided to adjust the budget as changes happen.

How does this sound to you?

To me, this sounds pretty bad, because there is an important distinction between adjusting the budget based on change requests and consuming the contingency reserve.

Continue ReadingContingency or re-baselining, what’s the difference?

Is an ERP implementation project just a project?

  • Reading time:5 mins read

image “Software projects are no different from other projects”.

This statement is being repeated over and over at project management courses and seminars, even endorsed in books.

It’s true that software (and ERP implementation, as a subset of software) projects have many traits in common with projects in other disciplines. But ignoring their specifics is almost as wrong as saying that software projects are completely different than other projects.

Continue ReadingIs an ERP implementation project just a project?

5th rule of agile ERP: interface where possible

  • Reading time:5 mins read

imageOne of the biggest absurdities about ERP systems springs from the very word we use so often when describing ERP: integrated.

ERP is an integrated system: it integrates all data and processes into a single application. Different modules look over different aspects of data and processes, but a change in one module automatically reflects in all others.

A fantastic concept. When it was invented, it streamlined processes, boosted productivity and eliminated overhead and error.

So, whenever a new functionality is needed by a company, it should be integrated into the ERP, to benefit from the integrated system. Right?

Wrong.

Continue Reading5th rule of agile ERP: interface where possible

Why is add-on better than custom, any day?

  • Reading time:5 mins read

image Implementation is like marriage. For better or worse, you choose a piece of software, take it under your roof and commit to it for a long term, so help you God.

And as in marriage, if you want to live happily ever after with your new software, the my way or the highway attitude doesn’t help much—you must be open to compromise.

Last Monday, I argued for avoiding customizations if at all possible, an argument I stand by firmly. It’s like forcing your wife to color her hair pink. I don’t know about your wife, but mine doesn’t color her hair pink. If you like it pink, it’s probably something to think about before turning your yes in.

But NAV is NAV, isn’t it? It has what it has, and if I need it different, I have to customize it, right?

Wrong. You can compromise.

Continue ReadingWhy is add-on better than custom, any day?

Default database approach

  • Reading time:6 mins read

Last Friday, while enjoying a not-at-all healthy Salisbury steak with cheese, I had an interesting discussion with a partner: should NAV consultancies create default databases?

A default database (in this context) is a packaged solution built upon standard Microsoft Dynamics NAV, where a consultancy has introduced a number of features that they sell to all their customers as the standard solution, instead of standard NAV. The modifications to standard NAV can range from simple report adornments to minor feature improvements  to full-scale horizontal or vertical functionalities.

Continue ReadingDefault database approach

The Sure Step Rule of Taxi Fare

  • Reading time:4 mins read

Some time back, as I was riding a taxi from Prague airport to Holiday Inn hotel, I wondered about the fixed price I was about to pay for the ride.

– “Airport to city is 700 flat.” – said the driver when I asked how much approximately will it cost.

Common wisdom goes that flat rates mean you get it worse than if it wasn’t flat. Indeed, if it was on meter, and if the driver took the shortest route (I had a GPS device on me, I could’ve easily checked it!), the fare would’ve been lower. And yet, I decided I loved the flat rate.

Continue ReadingThe Sure Step Rule of Taxi Fare

Diagnostic Phase – a signpost for implementation

  • Reading time:5 mins read

Each phase of Microsoft Dynamics Sure Step methodology is equally important in an implementation project. You could argue that analysis is the most important, or that design is the most important, or that operation is less important. I’ll paraphrase Scott Adams here and ask: how one phase can be more important if each of them is completely necessary? Well, except for Diagnostic phase.

Continue ReadingDiagnostic Phase – a signpost for implementation

A case for Sure Step: how Sure Step brings project success

  • Reading time:8 mins read

Methodology is a tough topic. There are good methodologies, there are bad methodologies, there are good methodologies gone bad. Methodology is not a silver bullet, it won’t just make any problems disappear, and is hardly ever the single source of success or failure. But a methodology can be a major contributor to success. I could put it this way: you stand much better chances of success if you apply a methodology, then if you don’t. With something as critical as an implementation of business software, methodology is a key success factor. According to Jim Johnson of Standish Group, it’s number nine on their ten identified most important success factors.

Continue ReadingA case for Sure Step: how Sure Step brings project success

Serial Numbers Conundrum

  • Reading time:6 mins read

A blog reader has asked me for help about an allegedly strange behavior of items with serial number tracking. They had a customer who had serial number tracking switched on for an item with FIFO costing method. Whenever they posted a sales transaction, they chose the serial number manually. Then they noticed a puzzling behavior.

No matter the specification of the serial number on the sales lines, Microsoft Dynamics NAV seemed to be closing the item entries according to FIFO method. This effectively allowed a serial number to be sold twice (or more). They called for help.

Continue ReadingSerial Numbers Conundrum

Standard enemy

  • Reading time:4 mins read

The biggest jeopardies often lurk where we least expect them. When implementing an ERP system such as Microsoft Dynamics NAV, what should be one of our best allies, turns out to be our mortal enemy. It has a simple name: The Standard. Standard processes, standard functionality, standard documents, standard system. All these gizmos can turn into gremlins in a blink of an unattentive eye.

Standards are tricky. If during due dilligence, or diagnostic or analysis phase, we hear the prospect or customer utter the word “standard”, what do we instinctively do? Well, in a standard system, it’s pretty obvious what the standard is, and when the customer says that they “just have standard processes” it means that these processes are just covered with such a standard system, right? So we instinctively tend to skip the more detailed analysis of these, because after all, they are standard.

Continue ReadingStandard enemy